You can manage asset routes using the Manage Asset Route page from the Maintenance Super User responsibility. Use the Manage Asset Route page to update the default values set during the asset route definition.
This page enables you to:
Add sequence numbers to associated assets of the asset route.
Add setup controls to allow route update at work order and cost distribution percent update at work order.
Add setup control to allow the capture of Quality results at work order completion for associated assets of the asset route.
Attention: You must use the Defining Asset Route form to define an asset route. See Define Asset Routes
Navigate to the Manage Asset Route page (Maintenance Super User > Assets > Capital).
Enter criteria to search for an asset.
Click the Go button.
Select the radiobutton for the asset number.
Select the Manage Asset Route in the View drop-down list.
Click the Go button, and the Manage Asset Route page appears.
Optionally select one of the following check boxes:
Allow Route Updates At Work Order:
Select this option to modify the asset route at the WO level , by adding assets to the route or by deleting existing assets from the route. These changes apply to the work order route and does not impact the asset route definition.
If you do not select this option, then you cannot add or delete associated assets.
Enable Cost % Updates At Work Order:
Select this option to update and save the cost percentage of associated assets at the work order level, which will take effect only for the only respective WO cost allocation. Routes defined with equal cost allocation also can be updated at the WO.
If you do not select this option, then the cost percentage update for assets at the work order level is not available. The cost allocation will be based on the percentage values defined at the asset route definition.
Enable Route Assets Quality Results:
Select this option to capture Quality Results for associated assets during work order transactions such as Operation Completion, Work Order Completion. You will be able to enter quality results on the Work Order Completion and Operation Completion pages.
If you do not select this option, you will be able enter quality results for the asset route only. You will not be able to enter quality results for the associated assets.
Enter a unique value in the Sequence Number for the existing associated asset.
Click the Add 3 Rows icon to add associated assets to the route. Enter a sequence number for the new asset.
Enter a percentage value in the Cost Distribution % for each of the associated assets.
Click the Allocate Route Cost Equally button to set or reset the cost percentage value to be equal for all assets in asset route.
The Route Cost Allocated Equally checkbox is selected after you click the Allocate Route Cost Equally button.
Optionally change the Active Start Date and Active End Dates. The default values come from the asset route definition.
Save your work.