The Flow Schedule Details window enables you to view and modify Flow schedules at the detail level of the assembly. You can access this window from the Line Scheduling Options or Flow Schedule Summary windows. If you are navigating from the Line Scheduling Options window, you can filter your search by entering field and operator values. All details within criteria specified display on the Flow Schedule Details window. If you are accessing this window from the Flow Schedule Summary window, only the schedules selected display.
When Oracle Flow Manufacturing is integrated with Oracle Advanced Supply Chain Planning, manually entered Build Sequence values cannot exceed 9 digits. This restriction does not apply to Flow Manufacturing when not integrating with these products.
Note: Only flow schedules can be maintained through this window. Repetitive schedules and discrete jobs are displayed but cannot be modified.
Navigate to the Line Scheduling Workbench Options window.
Enter values, and choose All Flow Schedule Details. See: Line Scheduling Workbench Options Window
The Find Flow Schedule Details window displays.
Enter search criteria, or leave all fields blank to retrieve all records.
To filter your search, enter a search string by selecting Field values and an operator in the Condition field
You can use one string or several strings.
You can also select the Folder menu to customize your display and save your Find criteria.
Customizing the Presentation of Data in a Folder, and Searching for Data
Choose Find.
The Flow Schedule Details window displays information according to your search criteria.
Navigate to the Flow Schedule Summary window, select one or more assemblies.
Choose Details.
The Flow Schedule Details window displays information on the assemblies selected in the summary window.
Navigate to the Flow Schedule Details window.
This window displays fields for Assembly, Build Sequence, Completion Date, Quantity, Completed Quantity, Order Number, Order Line, Order Requested Date, and Unit Number.
You can modify some values including Build Sequence, Completion Date, and Quantity fields.
Note: When Oracle Flow Manufacturing is integrated with Oracle Advanced Supply Chain Planning, manually entered Build Sequence values cannot exceed 9 digits.
Save your work.
You can access the following windows:
Unscheduled Orders: Displays the Unscheduled Orders window. See: Viewing Unscheduled Orders
Component Availability: Displays the ATP Results window to show the status of material used on your lines. See: Component Availability
Component availability checking is permitted only for items with the Check ATP item attribute set to Yes. See: Order Management Attribute Group