Lead-time

Lead-time Introduction

Lead-times are portions of the span of time from recognizing the need for an order to receiving the goods to inventory.

This topic reviews the lead-times that Oracle Advanced Supply Chain Planning uses to plan and schedule. It also explains concurrent processes, profile options, plan options, and planning parameters that affect lead-time calculations.

Setting Lead-times

Set lead-time values for the planning engine to use in the following source system forms:

The planning engine does not use subinventory lead-times from Oracle Inventory. These values are for the Oracle Inventory Min-Max planning process.

Lead-time Item Attributes

This topic describes the lead-time item attributes. You define them:

For more information, see Oracle Inventory User's Guide.

Lead-time Item Attributes Definition

You can enter the following lead-time item attributes:

Lead-times and Order Dates

The lead-times define dates that are associated with planned orders and scheduled receipts for these items:

Lead-time Item Attributes and Lead Time Calculation Concurrent Processes

If you run the following Oracle Bills of Material concurrent processes, they can update lead-time values that you may have manually set:

These concurrent processes update the following lead-time item attribute fields:

Decimal lead-time quantities denote times less then one day and are the result of the lead-time divided by 24 hours.

For more information, see Oracle Bills of Material User's Guide.

Safety Lead Time

Safety lead-time is a lead-time that you add to the normal lead-time of make and buy items. You use it to instruct the planning engine to schedule supplies in advance of the demand due dates that peg to them for the purposes of:

Safety lead-time is sometimes referred to as protection time or safety time

You can also complete supplies earlier than the demands that peg to them using transient safety stock levels. See Safety Stock. Use safety stock lead-time instead of transient safety stock if you want to have:

Safety stock lead-time is:

To set safety lead time:

When the planning engine schedules a supply subject to safety lead-time, it:

This example shows how to analyze plan information for items subject to safety lead-time:

image described in text

This example shows the plan information for the same demand position but using non-transient/transient safety stock planning. In the diagram, SS means safety stock and PAB means projected available balance.

image described in text

If you use safety lead-time:

Lead-time Item Attribute Notes

You can also view Preprocessing, Processing, Postprocessing, Fixed, and Variable in the Collections Workbench Items window and the Planner Workbench Items window.

The planning engine does not use Cumulative Manufacturing and Cumulative Total values. You may see them in lists of values when you are entering lead-times, for example, item attribute Planning Time Fence.

Total lead-time is not an item attribute. The planning engine calculates it in unconstrained plans to determine an order's Order Date. It:

The Calculate Manufacturing Lead-time concurrent process uses the same general calculation for Processing as the planning engine uses for Total Lead-time. The Calculate Manufacturing Lead-time concurrent process uses item attribute Lead-time Lot Size to calculate item attribute Processing. The planning engine uses actual order quantity to calculate the processing time for a specific planned order or scheduled receipt.

This diagram shows the relative use of Total Lead-time, Cumulative Manufacturing, and Cumulative Total.

Calculations of Cumulative Lead-time Attributes

image described in text

Calculated Supply Dates

For all plan types, the planning engine schedules planned orders and scheduled receipts based on Demand Due Date of the demand that the supply is pegged to. It calculates these dates:

Old Due Date, Old Dock Date, and Original Need By Date are the original dates from the source system for scheduled receipts.

You can view these dates in the Planner Workbench from among the Supply/Demand, Supply, and Demand windows.

Calculating Planned Order Demand Due Date

Oracle Advanced Supply Chain Planning takes into account the actual requirement date and the lead-times for calculating the planned order demand due dates. This provides more accurate lead-time offsets in aggregate planning time buckets.

The planning engine allows you to plan at aggregate time bucket levels like periods and weeks. It provides you easy identification of aggregate supply/demand mismatches and helps you make strategic decisions related to equipment and labor acquisition, sourcing etc. without generating needless details.

The planning engine's Memory Based Planner calculates the planned order demand due dates for dependent demands based on the actual requirement date with respect to lead-time. It saves the calculated requirement date based on the lead-time value for subsequent calculation.

The planning engine aligns all dates to the ends of time buckets. You can get more accurate dates by first performing dependent demand explosion followed by alignment.

Example

Consider an organization with an assembly A, which has components B and C.

Assembly

image described in text

The quantity per assembly for components B and C is 1.

The lead-time for assembly A = 4

The lead-time for sub-assembly B = 3

The lead-time for component C = 4

The organization follows a weekly planning bucket and working days are Monday through Friday.

An order quantity of 1 is placed for item A on Friday February 28.

The planning engine generates the following planned order demands:

Planned Order Demand Due Date Calculation

image described in text

Explanation:

Date Calculations for Manufactured Supplies

The planning engine uses work days from the manufacturing calendar to calculate dates for manufactured supplies, unless otherwise indicated.

Need By Date: The date that the material should ship or be in inventory for a next-higher level assembly. The earliest demand due date that the supply is pegged to.

Suggested Due Date: In an Unconstrained or Constrained - Enforce demand due dates plan this is the same as Need By Date. In a Constrained - Enforce capacity constraints plan this is the scheduled availability date of the supply. If the supply is constrained, the planning engine forward schedules from the constraint.

Suggested Dock Date: Demand Due Date. Dock Date is the day by which all shop floor operations are complete. Manufactured supplies do not have a Postprocessing lead-time.

Suggested Ship Date: Blank

Suggested Start Date: Suggested Due Date - Production duration. The day that you should begin shop floor operations.

lead-time offsetting begins only on a workday of the workday calendar. For example:

Production Duration:

Suggested Order Date: Planned order Start Date - Preprocessing. The date on which you should place the order. For a scheduled receipt, this field displays the date the date that it was created.

This diagram shows dates calculated for manufacturing supplies.

Dates Calculated for Manufacturing Supplies

image described in text

Date Calculations for Manufactured Supply Components

The planning engine calculates the component due dates of a manufacturing supply order according to your setting of the plan option Material Scheduling Method.

For value Order Start Date, the component due date is the supply Start Date.

For value Operation Start Date:

Purchased Supply Lead-times and Approved Supplier Lists

If the item of the purchased supply has an Approved Supplier List, the planning engine:

You can view Approved Supplier List planning attributes in the Collections Workbench and the Planner Workbench, Items window, Sources tabbed region, and select Supplier Capacity.

Date Calculations for Purchased Supplies

The planning engine uses work days from the receiving organization calendar to calculate dates for purchased supplies, unless otherwise indicated.

Need by Date: Date that the material is required to satisfy demand.

Suggested Due Date:

Suggested Dock Date:

Suggested Ship Date: Dock Date - Production duration

Production Duration:

Suggested Start Date: Ship Date

Suggested Order Date: Start Date - Preprocessing. For a scheduled receipt, this field displays the date the date that it was created. In Collections Workbench, purchase order create date. The planning engine calculates this date using the organization manufacturing calendar.

This diagram shows the calculations for purchased supplies.

Calculated Dates for Purchased Supplies

image described in text

Date Calculations for Transfer Supplies

The planning engine uses work days from the receiving organization calendar and shipping organization calendar to calculate dates for transfer supplies.

Need By Date (receiving organization calendar): Date material is required to satisfy demand.

Demand Due Date (receiving organization calendar):

Suggested Dock Date (receiving organization calendar): Due Date - Postprocessing

Suggested Ship Date (shipping organization calendar):

Suggested Start Date (shipping organization calendar):

Suggested Order Date (receiving organization calendar):

For a scheduled receipt, this field displays the date the date that it was created.

This diagram shows calculated dates for transfer supplies in an unconstrained plan. The planning engine calculates production duration differently for the source organization and the destination organizations; therefore, the dates in your plan may not line up as accurately as they appear in this diagram. If material is scheduled inside of these lead-times, planners can determine what action to take on the compression messages.

Calculated Dates for Transfer Supplies, Unconstrained Plan

image described in text

This diagram shows that, in constrained plans, Need By Date and Demand Due Date in the shipping organization should be the same as planned order Ship Date in the shipping organization.

Calculated Dates for Transfer Supplies, Constrained Plan

image described in text