Deleting Resource Requirements

You can delete resource requirements as you update operations. You cannot delete resource requirement that have pending transactions, you cannot delete resource requirements that have been transacted even if their due quantity is zero. If you delete an operation, the resources associated with it are automatically deleted.

arrow icon   To delete resource requirements:

  1. Navigate to the Operations window.

  2. Select the operation Sequence.

    The operation Sequence specifies from which operation the resource is to be deleted.

  3. Choose the Resources button. The Resource Requirements window appears.

  4. In the Main tabbed region of the Resource Requirements window, select or enter the resource Sequence number.

  5. Select the resource Name.

    You can delete a resource requirement regardless of the status of the job or repetitive schedule. You cannot delete a resource that has been charged at an operation (applied quantity exists) or that has pending resource transactions.

    If you delete an operation from a job or repetitive schedule, you may want to reschedule the job or repetitive schedule to correctly reflect the start and completion dates.

    You cannot delete a PO move or PO receipt resources or the operations they are assigned to if purchase requisitions (either approved or unapproved) or purchase orders exist for these resources.

  6. Choose Delete Record from the Edit Menu.

  7. Save your work.