Implementing Planning Recommendations

Overview of Implementing Planning Recommendations

After you have reviewed your material plans, you are ready to release the planning recommendations. You can:

Alternatively, you can enable the planning process to automatically release planned orders, without modification to dates and quantities or implementation details. However, you must manually implement and release repetitive schedules. See: Auto-release Planned Orders.

Note: You cannot release kanban items. These items have item attribute Release Time Fence set to Do Not Release (Kanban) in Oracle Inventory.

The planning process will generate planned orders against these items, but you will not be able to release them into Purchasing or Work in Process.

A warning message displays informing you when releasing MPS planned order in MRP