You can assign burden schedules to project types, projects, and tasks. When you assign schedules to a project type, the schedules are the default schedules for projects and tasks that use the project type. Assigning burden schedules to project types allows you to implement company policies; for example, you can implement a policy that requires all projects of a particular project type to maintain the same multipliers for internal costing purposes.
You can change the default schedule for a project or task. You can also override default schedules at the project and task level by using burden schedule overrides. Burden schedule overrides generally reflect multipliers that have been negotiated specifically for a particular project or task.