Update Project Summary Amounts

This process updates the project summary amounts with new cost, commitment, and revenue transactions and any new baselined budget versions.

You can run this process as many times as you want.

Process Submission

From the Submit Request window, submit one of the PRC: Update Project Summary Amounts processes:

See: Submitting Requests

Selected Parameters

From / To Project Number. Optionally, enter a range of project numbers to update summary amounts for the projects in the specified range. Leave the parameters blank to update summary amounts for all projects.

Project Type. Optionally enter a project type to limit the update of summary amounts to projects of the selected project type.

Through Date. Optionally enter an end date for the process.

If you do not enter a date, or the date you enter is equal to or later than the current reporting period end date, the process summarizes all selected data through the current reporting period. If you enter a date earlier than the end date of the current reporting period, the process summarizes data through the date you enter.

Summarize Cost. Enter Yes if you want the Update Project Summary Amounts process to summarize cost amounts.

Expenditure Type Class. If you are running the Update Project Summary Amounts process for one project, you can optionally select one expenditure type class to update summary amounts for.

Summarize Revenue. Enter Yes if you want the Update Project Summary Amounts process to summarize revenue amounts.

Summarize Budgets. Enter Yes if you want the Update Project Summary Amounts process to summarize budget amounts.

Budget Type. Select a budget type or financial plan type for which you want to summarize amounts.

Note: You must maintain forecast amounts for a project in either a financial plan type or a budget type of forecast cost or forecast revenue to prevent the Update Project Summary Amounts process from adding up forecast summaries in the financial plan and budget.

Summarize Commitments. Enter Yes if you want the Update Project Summary Amounts process to summarize commitment amounts.

Resource List Name. If you are running the Update Project Summary Amounts After a Resource List Change process, you can optionally select the resource list that you want the process to use.

Note: The Update Project Summary Amounts process only uses the resources list. You can migrate a resource list to a planning resource list and Oracle Projects copies changes in the resource list to the migrated planning resource list, but not vice versa. You must make changes in the original resource list to ensure that the Update Project Summary Amounts process correctly summarizes amounts for display.

Generate Report Output. Enter Yes if you want the process to generate a report.

Reports

The following reports show you the results of this process. Report amounts are in the project currency.