Attributes Transferred

The tables below list the workplan and financial attributes transferred between Oracle Projects and Microsoft Project, the direction of data transfer, the Oracle Projects fields, and the corresponding fields in Microsoft Project. For successful integration, columns must not contain other information that Microsoft Project Integration uses.

Workplan Attributes

The following table lists the task planning attributes for Oracle Projects and Microsoft Project.

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Task Name Task Name Both ways
Task Number Unique ID or Text5 or Outline Number - Unique ID and Outline Number: Microsoft Project to Oracle Projects
- Text5: Both ways
Task Manager Text16 Oracle Projects to Microsoft Project
Task Manager ID Text6 Both ways
Task Description Notes Both ways
Task Priority Text10 Both ways
Task Outline Number and Level Outline Number and Level Both ways
Task Type Text18 Oracle Projects to Microsoft Project
Task Type ID Text7 Both ways
Scheduling Tool Task Type Task Type Both ways
Work Type Text17 Oracle Projects to Microsoft Project
Work Type ID Text8 Both ways
Service Type Code Text4 Both ways
Chargeable Flag Text2 Both ways
Billable Flag Text3 Both ways
Scheduled Start Date Start Microsoft Project to Oracle Projects
Scheduled Finish Date Finish Microsoft Project to Oracle Projects
Scheduled Duration: For task with no assignments Duration Both ways
Scheduled Duration: For task with assignments Duration - Both ways for fixed duration tasks
- Microsoft Project to Oracle Projects for fixed units and fixed work tasks
Actual Duration Actual Duration Microsoft Project to Oracle Projects
Transaction Start Date - Start1 for shared structures
- Start for split structures
Both ways
Transaction Finish Date - Start1 for shared structures
- Start for split structures
Both ways
Milestone Flag Milestone Both ways
Critical Flag Critical Microsoft Project to Oracle Projects
Constraint Date Constraint Date Both ways
Constraint Type Constraint Type Both ways
Early Start Early Start Microsoft Project to Oracle Projects
Early Finish Early Finish Microsoft Project to Oracle Projects
Late Start Late Start Microsoft Project to Oracle Projects
Late Finish Late Finish Microsoft Project to Oracle Projects
Free Slack (Free Float) Free Slack Microsoft Project to Oracle Projects
Total Slack (Total Float) Total Slack Microsoft Project to Oracle Projects
Task Effort Driven Flag Effort Driven Both ways
Level Assignments Level Assignments Both ways
Item Code Text14 Both ways
UOM Code Text15 Both ways
Dependencies: Predecessors Predecessors Both ways
Planned Efforts Works Both ways
Planned Cost Cost Microsoft Project to Oracle Projects when Calculate Cost Using Microsoft Project option is selected.

The following table lists the Oracle Projects fields and Microsoft Project fields for task progress attributes:

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Progress Status Code Text11 Both ways
Progress Overview Text12 Both ways
Progress Comments Text13 Both ways

Note: Microsoft Project receives only the first 255 characters from Oracle Projects.

Planned Work Quantity Number2 Both ways
Cumulative Work Quantity Number1 Both ways
Actual Effort to Date Actual Work Both ways
Estimated to Complete Effort Remaining Work Microsoft Project to Oracle Projects
Estimate to Complete Cost Cost6 Oracle Projects to Microsoft Project
Actual Start Actual Start Both ways if task has no assignments
Actual Finish Actual Finish Both ways if task has no assignments
Estimated Start Start3 Both ways
Estimated Finish Finish3 Both ways
Physical % Complete Text19 Both ways
Task Status Code Text9 Both ways

The following table lists the Oracle Projects fields and Microsoft Project fields for resource assignment planning attributes:

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Planning Resource Name Resource Name Both ways
Role Name Text2 Both ways
Unit of Measure Text3 Oracle Projects to Microsoft Project
Assignment Delay Assignment Delay Microsoft Project to Oracle Projects
Scheduled Start Start Microsoft Project to Oracle Projects
Scheduled Finish Finish Microsoft Project to Oracle Projects
Planned Quantity Work Both ways
Planned Cost Cost1 Both ways

The following table lists the Oracle Projects fields and Microsoft Project fields for resource assignment progress attributes:

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Actual Start Actual Start Both ways
Actual Finish Actual Finish Both ways
Actual Effort Actual Work Both ways
Estimate to Complete Effort Remaining Work Microsoft Project to Oracle Projects
Actual Cost Actual Cost Oracle Projects to Microsoft Project
Estimate to Complete Cost Cost2 Both ways

The following table lists the Oracle Projects fields and Microsoft Project fields for the resource attributes:

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Planning Resource Alias Name Oracle Projects to Microsoft Project
Resource Class Resource Type Oracle Projects to Microsoft Project
Resource Unit of Measure Text2 Oracle Projects to Microsoft Project
Burden Rate Standard Rate Oracle Projects to Microsoft Project

Financial Attributes

The following table lists the Oracle Projects fields and Microsoft Project fields for financial attributes:

Oracle Projects Field Microsoft Project Field Direction of Data Transfer
Baseline Cost Cost 10 Oracle Projects to Microsoft Projects
Billable/Capitalizable Text3 Both ways
Burdened Cost Cost Microsoft Project to Oracle
Chargeable Text2 Both ways
ITD Burden Cost Cost 2 Oracle Projects to Microsoft Projects
ITD Raw Cost Cost 1 Oracle Projects to Microsoft Projects
Latest Published Cost Cost 9 Oracle Projects to Microsoft Projects
Microsoft Project to Oracle Projects Quantity
Projects Revenue Cost
PTD Burden Cost Cost 6 Oracle Projects to Microsoft Projects
PTD Raw Cost Cost 4 Oracle Projects to Microsoft Projects
Raw Cost Cost Microsoft Project to Oracle Projects
Revenue Cost3 Oracle Projects to Microsoft Projects
Service Type Code Text4 Both ways
Work Microsoft Project to Oracle Projects
YTD Burden Cost Cost 7 Oracle Projects to Microsoft Projects
YTD Raw Cost Cost 5 Oracle Projects to Microsoft Projects

The integration process also uses several project-level columns in Microsoft Project. However, you should not access these columns to view or change information for the Project Summary Task using Microsoft Project Integration or any of the related features in Microsoft Project.

The following business rules apply to sending attribute values from Microsoft Project to Oracle Projects:

Related Topics