IDV Lines

The Lines tab consists of the following fields:

You can also perform actions such as Update, Duplicate and Delete for each line. The Delete Action deletes a line from the award. If you are deleting a CLIN that has SLINs associated to it, the entire CLIN/SLIN structure is deleted. If you delete a SLIN only, the SLINs below it move up one level in the structure for that CLIN/SLIN hierarchy. The Duplicate action makes a copy of the line and places it below the original line. The Update action enables you to view the Update Line page and enter/edit additional line information.

To enter line information in the IDV, click the Lines tab. Enter the relevant information on the line, and then click the Update icon (pencil icon) to enter further details in this tab.

More on CLINs / SLINs:

For more information on exhibits and CDRLs, please refer to the section ELINs and CDRLs in the Awards chapter in this guide.

Line Level Actions

Copy Lines action

The Copy Lines : Specify Copying Options page enables you to copy CLIN/SLIN structures and option lines in the same CLM document. The copy alternatives are:

In addition, the Define Need By Date and Period of Performance Dates region enables you to enter a specific date or obtain a derived date. A derived date is calculated from the existing date values by the system after you enter a duration, for example, 1 month after the Need By Date of the source line.

The Define Option Dates region enables you to either enter a specific date or obtain a derived date. A derived date is calculated from the existing date values by the system after you enter a duration, for example, you can specify that the Option Start Date should be set to 3 months earlier than the Need-By Date derived for that line.

Click Apply to initiate the copy and when you return to the Lines page, you will see the copied lines with the appropriate dates and CLIN/SLIN structures and options, if any.

Fields in the Main region

For more information on Pricing, please refer to the appendix - Common CLM Functionality.

The Option checkbox in the Option region enables you to specify whether the line should be treated as an Option line. You can convert a regular line into an option line, and an option line into a regular line by toggling this check-box. The system displays a warning before allowing the change. Click Continue to proceed with the conversion or Cancel to retain the existing lines as is.

If you wish to associate a base line to your option line, select a Base Line Number from the LOV. The option line may or may not be associated with a base line.

Option Num (Number) is a system generated number and is non-updateable.

Option Dates are mandatory fields.

Fields in the Federal Customer Designation region

The fields in this region provide information that enable the IDV to designate a particular classification code or program to the item being procured.

Fields in the Additional Item Information region

The fields in this region enable you to provide specific details about the item that will be ordered. The fields described below are free-text fields are not validated in the system.

Fields in the Ordering Constraints region

Order Start Date: The date in which orders can begin to be issued against the IDV line. When creating orders against an IDV, the start date in conjunction with the end date define the period in which orders can be created against the IDV line. The Order Start Date is equal to or after the Effective Date. The Order End Date should be after the Order Start Date. When orders are created referencing the IDVs, the Order Effective Date should be within this date range (Order Start Date and Order End Date). This date validation is carried out when the order is submitted for approval.

Order End Date: Date in which orders can no longer be issued against the IDV line. When creating orders against an IDV line, the start date in conjunction with the end date define the period in which orders can be created against the IDV line. This Order End Date (at the line level) should be equal to or less than the Order End Date at the header level. This validation occurs only when the Order Start Date and Order End Date are entered at the header level.

Maximum Total Amount: The maximum amount that can be ordered over the life of the contract line. This field is used to ensure that a maximum amount is ordered against an IDV line. For example, if the Maximum Total Amount is $1000, all order lines created against the IDV line cannot (in total) exceed this amount. Therefore, you could have 3 orders, Order #1 - Line 0001 for $500, Order #2 - Line 00001 for $250 and Order #3, Line 0001 for $200, all of which total $950 and does not exceed the maximum amount. However, if Order #4 is created with line 0001 for $100 and references the IDV line, the system will prevent the order from being approved because it exceeds the constraint.

Minimum Total Amount: The minimum Amount that must be ordered over the life of the contract line. This field is used to ensure that a minimum amount is ordered against an IDV line. For example, if the IDV has a Minimum Total Amount of $80, and the IDV line amount is $100, then a minimum $80 of orders will be created against the IDV line. So there could be 3 orders created and in total they should exceed $80 during the life of the contract. This field is user-enterable and is not validated by the system.

Maximum Total Quantity: The maximum quantity that can be ordered over the life of the contract line. This field is used to ensure that a maximum quantity is ordered against an IDV line. For example, if the Maximum Total Quantity is $1000, then all order lines created against the IDV line cannot (in total) exceed this quantity. Therefore, you could have 3 orders, Order #1 - Line 0001 quantity 500, Order #2 - Line 00001 quantity 250 and Order #3, Line 0001 quantity 200, all of which total 950 and does not exceed the maximum amount. However, if Order #4 is created with line 0001 for quantity 100 and references the IDV line, the system prevents the order from being approved because it exceeds the constraint.

Minimum Total Quantity: The minimum quantity that must be ordered over the life of the contract line. This field is used to ensure that a minimum quantity is ordered against an IDV line. For example, if the IDV has a Minimum Total Quantity of 80, and the IDV line amount is 100, then a minimum 80 of orders will be created against the IDV line. So there could be 3 orders created and in total they should exceed 80 during the life of the contract. You can manually ensure that the minimum is met procedurally via reports/queries and the enforcement is typically done as a part of the contract close-out procedures.

Maximum Per-Order Amount: The maximum Amount that can be ordered for the contract line on an individual order. This field is used to ensure that an individual order meets the maximum amount required for an IDV line. For example, if the IDV has a Maximum Per-Order Amount of $120 when an order is created against the IDV line it must have a total line amount of $120 or less. If the amount is greater than $120 then the order will not be approved.

Minimum Per-Order Amount: The minimum Amount that must be ordered for the contract line on an individual order. This field is used to ensure that an individual order meets the minimum amount required for an IDV line. For example, if the IDV has a Minimum Order Amount of $80 when an order is created against the IDV line it must have a total line amount of $80 or greater. If the amount is less than $80 then the order will not be approved.

Maximum Per-Order Quantity: The maximum quantity that can be ordered for the contract line on an individual order. This field is used to ensure that an individual order meets the maximum quantity required for an IDV line. For example, if the IDV has a Maximum Per-Order Quantity of 100, when an order is created against the IDV line it must have a quantity of 100 or less. If the amount is greater than 100 then the order will not be approved.

Minimum Per-Order Quantity: The minimum quantity that must be ordered for the contract line on an individual order. This field is used to ensure that an individual order meets the minimum quantity required for an IDV line. For example, if the IDV has a Minimum Per-Order Quantity of 50, when an order is created against the IDV line it must have a quantity of 50 or greater. If the quantity is less than 50 then the order will not be approved.

Total Amount Ordered: This is a calculated field that tracks the total amount that was ordered against the IDV line. This field is utilized to determine how much of the IDV line has already been ordered.

Total Amount Remaining: This is a calculated field that displays the amount for the IDV line that has not yet been ordered. This field is utilized to determine how much of the IDV line is left to order.

Total Quantity Ordered: This is a calculated field that tracks the total quantity that was ordered against the IDV line. This field is utilized to determine quantity already ordered for a given IDV line.

Total Quantity Remaining: This is a calculated field that displays the quantity for the IDV that has not yet been ordered. This field is to determine how much of the IDV line is left to order.

Price Breaks region

The Price Breaks region enables you to enter price breaks for the IDV. For example, the following price breaks could be entered:

Quantity Break Price
1 - 10 100
11 - 20 90
21 - 30 80
more than 30 70

You can also enter the Discount field to calculate the price break. Enter the effective dates to indicate the time limits for the price breaks.

Organize Lines

The Organize Lines page consists of 2 regions: Current Structure (source) and Target Structure (destination). Select one or more lines by clicking on the Select checkbox in the Current Structure region. Then select the type of move you wish to perform using the Select Action LOV in the Target Structure region. Select from one of the 3 possible values: Move After Selected Line (moves the line after the line you selected in the Edit Lines page), Move Before Selected Line (moves the line above the line you selected in the Edit Lines page) and Move as sub-line(s) under selected line (moves a line as a SLIN under a CLIN).

The action Move as sub-line(s) under selected line is not applicable for :

Click Done to save and apply your changes and return to the Lines page. The Lines page displays, showing you the new structure of the lines.

Global Update for IDV Lines

Global Update enables you to add common field values for multiple lines or update common field values for multiple lines on draft CLM documents.

Navigate to the IDV Lines tab. Select one, multiple, or all lines (use the Select All link) and then click Global Update. The Global Update Lines page displays with the fields that you can update for multiple IDV lines.

If you want to add a new value to the lines, such as Order Start Date or Order End Date, enter the value in the Global Update Lines page and click Apply. If you want to update / replace the original field value(s) with a new field value, such as Maximum Total Amount or Min Total Quantity, select or enter the new field value and click Apply. A message confirming that the update was successful displays in the Update CLM IDV page. You can navigate to individual IDV lines to verify that the update has taken place for the fields you specified.

Note: You cannot blank out any existing values using Global Update. You can only update add or update a value.