Supply Demand Window

The Supply/Demand window displays information about supplies and demands and shows pegging information.

View the Supply/Demand Window

You can navigate to the Supply/Demand window from various node types such as items, organizations, plans, departments, and planning groups in the Navigator. In addition to the Navigator, you can also drill down to the Supply/Demand window from other windows such as the Vertical Plan window.

If you request this window from the Exception Details window, it displays supply information, demand information, or both types of information based on the exception type. For example, if the exception message is Demand satisfied using end item substitution, the Supply/Demand window displays demand information only.

To display the Supply/Demand window

  1. Select one or more nodes (using Ctrl-click) in the Navigator.

  2. Select [right-click] > Supply/Demand.

    The Supply/Demand pop-up menu displays the following options:

  3. To display the Supply/Demand window, click Supply/Demand.

    Supply/Demand window has five tabbed regions:

    Each tabbed region displays fixed fields:

    While each tabbed region shows different variable fields, you can access all of the Supply/Demand window variable fields using the Orders tab folder function.

Supply/Demand Window Notes

Internal Requisitions and Sales Orders

If you cancel an internal requisition and do not cancel the corresponding internal sales order, Planner Workbench:

Safety Stock

To analyze how the planning engine has planned to meet safety stock levels, select the supply and analyze the pegging details. The pegs between a transient safety stock level and supplies peg with supply quantity zero. This is because the supply pegs to a demand after the safety stock level expires; the peg to the demand has the quantity. The pegs between a non-transient safety stock level and supplies peg with quantities that meet the safety stock level. To understand safety stock pegging, see Safety Stock Pegging in Pegging.

Order Tabbed Pane

The following table provides a description of the fields displayed in the Order tabbed pane:

Fields Description
Order Type This refers to the supply or the demand type. For example, purchase order, sales order, planned order.
Sugg Due Date The planning engine populates this for demands and supplies. For more information, seeLead Time and the Planning Time Fence.
Qty/Rate Supply, demand quantity, or rate.
Order Number Identifies the supply or the demand record. For purchase orders, displays purchase order number, line number, release number, shipment number.
Action This refers to the action recommended by the planning engine. The possible values are:
- None
- Release
- Cancel
New Date After you firm a supply, you can specify a new date to change an existing planned order, a forecast, an MDS demand, a manual MDS demand, or a sales order.
New Qty After you firm a supply, you can specify the quantity to change an existing planned order, a forecast, an MDS demand, a manual MDS demand, or a sales order.
Order Priority Indicates the priority of a demand. The planning engine generates this number based on the priority rule used in the plan.
ABC Class Inventory ABC classification of the item.
Alternate BOM BOM Alternate bill of material name
Alternate Routing BOM Alternate routing name
Arrival Set Name On the sales order, the arrival set name designates lines that should arrive together at the customer site. Oracle Advanced Supply Chain Planning does not consider arrival sets but displays the field for information.
Bucket Type This refers to the bucket type that a demand falls under, such as Forecasts. The valid values includes day, week, and period.
Build Sequence This number indicates the order in which the work orders are sequenced.
Category Category of an item
Company Name Name of the company
Company Site Name of the company site
Component Yield Bills of material component yield for a component
Compression Days The planning engine calculates the number of days that the order needs to be scheduled in the past (earlier than the planning horizon start date). For more information on Orders with Compression Days, see Exception Messages.
Consumed Forecast For a forecast demand, this field indicates the quantity of the forecast that is consumed by sales orders.
Consumption Backward Days This indicates the number of days (backward) when a forecast can be consumed by sales orders.
Consumption Forward Days This indicates the number of days (forward) when a forecast can be consumed by sales orders.
Cube Total cube of the supply row
Cumulative Probability Not used in Oracle Advanced Supply Chain Planning.
Customer Customer name as it appears on the sales order or forecast.
Customer Site Customer ship to location
Days From Today The planning engine calculates the difference between the suggested due date and the plan launch date to populate this field.
Days Late For more information, seeLead Time and the Planning Time Fence.
Demand Class An attribute of a demand that is used to categorize demand.
Demand Lateness Cost Penalty cost for a demand
Description Item description
Destination Org The destination organization for an internal sales order.
Earliest Allowable Completion Time The planning engine calculates this to indicate the end of the scheduling window for the supply that allows sufficient time for the upstream activities to be scheduled.
Earliest Possible Completion Time The planning engine calculates this based on the constrained schedule for upstream supplies. It is the earliest time in which the supply can be completed.
Earliest Possible Start Time The planning engine calculates the difference between the earliest possible completion time and supply duration to populate this field.
End Date The end date of a bucketed forecast. This is used only in the Collections workbench. The planning engine does not populate the end date for Oracle Advanced Supply Chain Planning plans.
Expiration Date This indicates the expiration date for an existing lot.
Expired Demand The planning engine marks the demand quantity as expired if the demand is not met within specific number of days.
First Unit Completion Date Indicates the first unit completion date of the repetitive job.
First Unit Start Date Indicates the first unit start date of the repetitive job.
Fixed Leadtime For buy items, the processing lead time
Imp Qty/Rate Corresponds to the new quantity that you specify for an order when you release the order.
Implement Alternate BOM Alternate BOM is an alternate list of component items that you can use to produce an assembly.
Implement Alternate Routing An alternate manufacturing process that you can use to produce an assembly.
Implement As If you select an organization in the Order tabbed pane, you can release the order as a discrete job. If you select a supplier, you can release the order as a purchase order.
Implement Date Corresponds to the new date that you specify for an order when you release the order.
Implement Demand Class Demand Class of released order
Implement FUCD Implement first unit completion date for a repetitive job (editable)
Implement Firm Implement firm flag status (editable)
Implement Job Implement job number (not editable)
Implement Line Implement line for a repetitive job (not editable)
Implement Project Implement project name (editable)
Implement Source Org Implement source organization (editable)
Implement Status Implement work in process status (editable)
Implement Supplier Implement supplier (editable)
Implement Supplier Site Implement supplier site (editable)
Implement Task Implement task identifier (editable)
Implement Unit Number Implement starting unit number for unit effectivity (not editable)
Implement WIP Class Implement work in process class (not editable)
Implemented Quantity Previously implemented order quantities (not editable)
Internal Sales Order Internal sales order number
Intransit Lead Time This indicates the transit lead-time associated with a transfer order.
Item Item name
Item From Source Plan A flag that indicates whether the item is planned in some other plan. For example, when you feed an MPS supply plan to another plan such as MRP, the planning engine sets the flag for the item in the MRP plan.
Last Unit Completion Date Indicates the last unit completion date of the repetitive job.
Last Unit Start Date Indicates the last unit start date of the repetitive job.
Latest Acceptable Date Indicates the latest acceptable date for a sales order.
Line Line refers to the flow line.
Location Location refers to the supplier site or organization location.
Lot Lot refers to the lot number.
MRP Planning Method Planning method defined for the item
Material Available Date For more information, seeLead Time and the Planning Time Fence.
Min Possible Days Late This planning engine calculates the minimum number of days that the end demand is late because of a particular supply. Other supplies may also cause additional delay.
Min Possible Start Time This field is obsolete.
Model/Option Class This refers to the model or the option class to which the item belongs.
Need By Date For more information, seeLead Time and the Planning Time Fence.
Old Dock Date For more information, seeLead Time and the Planning Time Fence.
Old Due Date For more information, seeLead Time and the Planning Time Fence.
Order Date Type For more information, seeLead Time and the Planning Time Fence.
Order Margin Profit margin of an order
Original Item If the planning engine recommends end item substitution for a demand, the item field refers to the substituted item. This field stores the original demanded item.
Original Item Qty This indicates the demand quantity of the original item.
Original Need By Date Original need by date of the purchase order or the requisition. For more information, see Lead Time and the Planning Time Fence.
Original Order Quantity For forecasts, this is the original order quantity of the forecast before consumption or before the forecast expiration. For all other order types, this is the same as the demand quantity.
Original Quantity Original forecast quantity for a global forecast.
Origination This field indicates the source where the planned supply is created. The origin is either the planning engine or ATP.
Override Transit Times Not used in Oracle Advanced Supply Chain Planning. This is reserved for future use.
PO Line No Purchase order line number
Planned Arrival Date For more information, see Lead Time and the Planning Time Fence.
Planner Planner code
Planning Group The name of the planning group for which the material is being planned.
Planning Level The identifier assigned to a project in the planning group.
Probability This is not used in Oracle Advanced Supply Chain Planning.
Process Days This field indicates the number of days a planned order is scheduled for a repetitive schedule.
Product Family The product family to which the item belongs.
Project Number Project number. For more information, see Planning in Mixed Mode Environments.
Promise Arrival Date The date when you promise that the customer can receive the products.
Promised Ship Date The date when you promise to ship the products to the customer.
For more information, see Lead Time and the Planning Time Fence.
Qty by Due Date This indicates the supply quantity that is available by the demand due date.
Quantity in Process This field indicates the quantity of a supply that is released.
Recommended Oracle Shop Flow Manufacturing job information on collection workbench.
Release Errors This field displays the release validation errors.
Repetitive Repetitive schedule
Requested Arrival Date The date when the customer wants to receive the products.
For more information, see Lead Time and the Planning Time Fence.
Requested Ship Date The date when the customer wants the products to be shipped.
For more information, see Lead Time and the Planning Time Fence.
Reschedule Days This indicates the number of days in or out that a supply order is rescheduled. A negative value indicates that the order is rescheduled to an earlier date.
Rescheduled This flag indicates that the order is rescheduled.
Schedule Designator This is the supply schedule name for those supplies that you feed to a plan by using a supply schedule.
Schedule Group This refers to work in process schedule group.
Schedule Arrival Date The date on which the customer can receive the product.
For more information, see Lead Time and the Planning Time Fence.
Schedule Ship Date The date when the product needs to be shipped to the customer.
For more information, see Lead Time and the Planning Time Fence.
Service Level Not used in Oracle Advanced Supply Chain Planning.
Shared Supply A flag to indicate that this supply is shared among multiple demands.
Ship Method Ship method used for transfers and buy orders.
Ship Set Name On the sales order, the ship set name designates lines that should ship together. Oracle Advanced Supply Chain Planning does not consider ship sets. However, the field is provided for information.
Ship To Customer ship to location
Shipment Not used in Oracle Advanced Supply Chain Planning.
Source Order Priority This indicates the priority number on the actual demand record. This is different from the priority number calculated by the planning engine.
Source Org Name of the source organization
Source Supplier Name of the source supplier
Source Supplier Site Name of the source supplier site
Start Quantity This indicates the start quantity of a supply that can be different from the finished quantity owing to yield.
Subinventory Subinventory identifier on the supply document, demand document, or location of an on-hand.
Substitute Component Rank BOM substitute component rank
Sugg Dock Date For more information, see Lead Time and the Planning Time Fence.
Suggested Due Date The timestamp for the suggested due date in case of:
  • Past demand lines is 23:59:00 on a day before the plan date

  • On hand supply due date is 00:00:00 on the plan date

Suggested Due Date Before Bucketing The due date for Planned Order Demand and Model, Option Class or, Product Family Demand order types.
Sugg Order Date For more information, see Lead Time and the Planning Time Fence.
Sugg Ship Date For more information, see Lead Time and the Planning Time Fence.
Sugg Start Date For more information, see Lead Time and the Planning Time Fence.
Source Supplier The supplier company name.
Source Supplier Site The supplier company site name.
Task Number The identifier assigned to the task in a project.
UOM This is an item attribute (unit of measurement)
Unconstrained Earliest Possible Completion Time The planning engine calculates this based on the unconstrained schedule for those upstream supplies that allow minimum durations.
Unconstrained Earliest Possible Start Time The planning engine calculates the difference between the unconstrained earliest possible completion time and supply duration.
Unconstrained Latest Possible Completion Time The planning engine calculates this based on the unconstrained schedule for those downstream supplies that allow minimum durations.
Unconstrained Latest Possible Start Time The planning engine calculates the difference between the unconstrained latest possible completion time and the supply duration.
Unit Number This refers to the starting unit effectivity number.
Update Need By Date For more information, see Lead Time and the Planning Time Fence.
Using Assembly For planned order associated with demands, this field refers to the assembly with this item as a component.
VMI Yes indicates that the supply is for a VMI-enabled item.
WIP Status Status of the work in process. Some of the values are:
- Onhold
- Released
- Unreleased
Weight Weight of the order
WIP Start Qty Start quantity used for planning

Release Properties Tabbed Pane

The following table provides a description of the fields displayed in the Release Properties tabbed pane:

Fields Description
Implement Date Implement date (editable)
Imp Qty/Rate Implement quantity or rate (editable). The planning engine initially derives this value by dividing quantity by rate.
Implement As Implement as a work order or a purchase requisition (editable).
Implement Alternate BOM Implement alternate bills of material name (editable)
Implement Alternate Routing Implement alternate routing name (editable)
Implement Arrival Date Implement arrival date (not editable)
Implement Demand Class Implement demand class (not editable)
Implement Dock Date Implement dock date (not editable)
Implement FUCD Implement first unit completion date for a repetitive job (editable)
Implement Firm Implement firm flag status (editable)
Implement Job Implement job number (not editable)
Implement Line Implement line for a repetitive job (not editable)
Implement Project Implement project name (editable)
Implement Ship Date Implement ship date (non editable)
Implement Source Org Implement source organization (editable)
Implement Status Implement work in process status (editable)
Implement Supplier Implement supplier (editable)
Implement Supplier Site Implement supplier site (editable)
Implement Task Implement task identifier (editable)
Implement Unit Number Implement starting unit number for unit effectivity (not editable)
Implement WIP Class Implement work in process class (not editable)
Implemented Quantity Previously implemented order quantities (not editable)
Location Implement location for the source organization or the supplier site (not editable)
Order Type Type of order such as planned order, sales order, manual master demand schedule (not editable).
Quantity in Process Implement Quantity or Rate (editable for planned orders only)
Quantity/Rate Original order quantity (not editable)
Release Errors Alerts you to any problem that might have occurred during the process of release.
Suggested Due Date For more information, see Lead Time and the Planning Time Fence.

Sourcing Tabbed Pane

The following table provides a description of the fields displayed in the Source tabbed pane:

Fields Description
Source Org Name of the source organization
Source Supplier Name of the supplier
Source Supplier Site Name of the supplier's site
Company Name Name of the company
Company Site Name of the company site
Order Type Type of order
Quantity/Rate Quantity supplied by the source org
Suggested Due Date For more information, see Lead Time and the Planning Time Fence.

Line Tabbed Pane

The following table provides a description of the fields displayed in the Line tabbed pane:

Fields Description
Line A group of resources
Schedule Group This refers to work in process schedule group.
Build Sequence The sequence number indicating the order in which work orders are sequenced
First Unit Start Date The date on which the first unit belonging to a line is scheduled.
Last Unit Completion Date The date on which the last unit belonging to a line is completed
Last Unit Start Date The date on which the last unit belonging to a line is started
Order Type Type of order. For example, planned order, sales order.
Process Days This field indicates the number of days a planned order is scheduled for a repetitive schedule.
Quantity/Rate This indicates the rate per day for a repetitive schedule.
Repetitive Repetitive schedule
Suggested Due Date For more information, see Lead Time and the Planning Time Fence.
Using Assembly Name of the assembly. An assembly is an item that has a bill of material.

Project Tabbed Pane

The following table provides a description of the fields displayed in the Project tabbed pane:

Fields Description
Planning Group The name of the planning group for which the material is being planned.
Project Number The identifier assigned to a project in the planning group.
Task Number The identifier assigned to the task in a project belonging to a planning group.
Order Type Type of order. For example, planned order, sales order.
Quantity/Rate The quantity of the order.
Suggested Due Date For more information, see Lead Time and the Planning Time Fence.
Unit Number Unit number

Right-click Menu Options in the Supply/Demand Window

In addition to the folder options, the right-click pop-up menu displays the following options to navigate to other windows: